PM Update

Posted Date: 09/02/26 (04:50 PM)


Good afternoon, Bellevue Community,


Please see below for updates on the status of progress with the building.


Facilities

  • Cleaning and remediation: To ensure the remediation team addresses all potential sources of moisture, cleaning and remediation will continue tonight and into tomorrow morning (September 3).

  • Building insulation: Insulation projects are anticipated to be completed by tomorrow morning (September 3).

  • Testing: Air quality tests are scheduled for tomorrow afternoon (September 3). 

    • Results will be shared when available. 

Transportation

  • Status: No changes.


Thank you for your ongoing patience, flexibility, and partnership as we work to ensure a safe environment for our scholars. We will share our next update tomorrow morning.


With great appreciation,

Jason