PM Update
Good afternoon, Bellevue Community,
Please see below for this evening’s updates.
Facility Updates:
Remediation: Remediation has been completed in 7 of the 10 identified classrooms. The final 3 rooms will be completed tomorrow (September 7).
Testing: Air quality testing in the first 4 remediated rooms began today. The results will be shared when available. Testing in the remaining rooms will occur in stages tomorrow.
Air Quality & Humidity: Dehumidifiers and HEPA air scrubbers continue to operate throughout the building to reduce relative humidity, inhibit mold and mildew growth, and continuously clean the air.
Holiday Communication Schedule:
To keep you informed through the final stages of remediation and testing, we will send our next update tomorrow (September 7) at 5:00 pm.
Thank you for your patience, support, and partnership.
With great appreciation,
Jason